SAFE - WP7 - Valorisation and Dissemination
Owner DE
Resource allocation
| Partner | Manager - days | Research - days | Technical - days | Admin - days |
| UK | 6 | 7 | 2 | 0 |
| DE | 20 | 24 | 4 | 20 |
| ES | 6 | 7 | 2 | 0 |
| RO | 6 | 7 | 2 | 0 |
| NL | 6 | 7 | 2 | 0 |
| CZ | 6 | 7 | 2 | 0 |
| BG | 6 | 2 | 0 | 0 |
Outcomes
Phase 1
Press releases to launch the project
Planning calendar in place for conferences and exhibitions
Meetings arranged with EuroMPs
project Brochure
Phase 2
End of phase report
Phase 3
End of phase report
Phase 4
Dissemination and publicity programme complete
End of phase report