Uk - End of phase 1 report

RETURN TO INDEX PAGE

LDV INGOT project End of Phase 1 -  31st March 2010

Summary of resources used

Management days used all partners

Work Package Days used Balance Comment
1 30 13 Any shortfall to be made up by partners. Setting up management systems, kick off meeting planning, initial liaison with WP managers. Liaison with subcontractors. Liaison with e-skills and regulators. Re-scheduling work due to delays caused by e-skills.
2 1 1 Planning training and coordinating with other WPs
3 11.5 15.5 Planning and coordinating questionnaire
4 1 3 Liaison with WP manager to plan input, input to planning and editing the handbook.
5 6 11 Manage translations - delays caused by e-skills and agreement of entry level criteria
6 9 30 Consultations with IT teachers and practitioners on needs. Observation of presentations of researchers on the key software packages and issues identified, discussing planning different structures of the manual
7 19 48 Planning web based games. Coordinating review of materials and suggestions, liaison with external pedaogical adviser.
8 6 26  Design data collection instruments
9 5 14 Liaison with BETT conference organisers. Planning flyer and publicity brochures.
Total 88.5 161.5  
Sub-contract Tech 50%-6000 50%  Separate reporting
Sub-contract Ped 25% - 3000 75% Separate reporting

 Research and training days used all partners

Work package
Days used Balance Comment
1 0 0 No days allocated
2 95 62 Partner training and cascade to other assessors. Support for e-learning development materials, e-mail/skype support and partner trainining sessions. Modifications to meet e-skills changing requirements.
3 35 39 Researching Eurybase for relevant info. Devise questionnaire, deal with partner queries. Proof read and feedback on questionnaire
4 11 20 Training in the use of Drupal/content management.  Research national frameworks and link to assessor guidance support handbook production.
5 61 195 Translation of assessment criteria and certification site. Translation of web support units WP7 (partial)
6 29 66 Research up to date sources, FOSS projects, Sourceforge, Open Source Schools Project, mailing lists, forums.
7 33 68 Developing open source web puzzles to support units, ITQ support course and web software support using Google sites
8 8 42 Research project QA needs to inform design of data collection instruments. Liaison with external adviser.
9 11 109 Attend BETT conference.  Preparation of publicity folder. Preparation of text and design for information guide leaflet, research avenues and contacts for dissemination
Totals 283 601 Any shortfall made up from additional partner contribution

Technical support all partners

Work package Days used Balance Comment
1  1 1 Liaison with subcontractor on technical issues
2 2 2 Small internal tech issues
3 6 7 Devise database prototype, test questions and cope with translation issues.
4 7 20 Technical design of handbook, moving information between CMSs.
5 0 0 Subcontracted - major implementation of technical support systems for translation for both certification and community sites
6 6 3 Testing target packages.
7 5 15 Dealing with browser issues, developing the delivery mechanism
8 0 3 No input yet needed
9 0 0

Subcontracted

Totals 27 51  
Mostly subcontracted

Subcontract through partner 1

Extend certification site to include regional management

Prepare certification and learning sites for language translations

Day to day support for technical issues

Improve front page

Enhance user-interface and help files. Start planning better integration between certification site and learning site.

January 2010 - March 2010.  - 6000 Euros paid in 2 installments

Administration

Work package
Days used Balance Comment
1 14.5 27.5  Support for management.
2 10 13 Travel arrangements, supporting e-learning development and training sessions
3 7 13  Support for developing web questionnaire on web site in multiple languages.
4 10 27 Print and proof handbook, liaison with WP leader. Support data transfer and web site appraisal.
5 15 51 Administrative support for translation work.
6 16 69  Support for info gathering and documentation
7 23 38 Support for developing the web site learning materials
8 5 18 Support development of data collection instruments and liaison with external ped agogical adviser
9 9 32  Support production of flyers, attendance at  BETT and general distribution.
Totals 109.5  1102  

Travel and subsistence

Work package
Travel
Balance Subsistence Balance Comment
1 1014.40 1385.60 420.00 4860.00 75% of these figures is grant
2 844.51 1355.49 1730.00 4543.00 Held back by wait for e-skills on entry level criteria. Will catch up by end of phase 2
3 903.78 -103.78 650 2632 Need to vire from subsistence to travel.
4 0 0 0 0 No travel and subsistence budget for this WP
5 0 0 0 0 No travel and subsistence budget for this WP
6 694.90 905.10 945 3207 Project meeting in Prague
7 0 0 0 0 No travel and subsistence budget for this WP
8 800.00 800.00 1080.00 4077.00 Meetingin Prague
9 26.22 7973.78 480.00 29928.00 Mainly for conferences and exhibitions in Y2.
Misc costs   Room hire in Prague
Totals 4283.81   5305.00 62920.19  

External Pedagogical Support - Subcontract

Meet with project manager

Review existing NWLG support materials

Review pedagogical model

Write report with recommendations

December 2009 - March 2010.  3000 Euros

UK

Management days used

Work Package Days used Balance Comment
1 16.5 18.5 Any shortfall to be made up by partners. Setting up management systems, kick off meeting planning, initial liaison with WP managers. Liaison with subcontractors. Liaison with e-skills and regulators. Re-scheduling work due to delays caused by e-skills.
2 1 1 Planning training and coordinating with other WPs
3 1 2 Liaison with WP manager to fi overall project
4 1 1  Liaison with WP manager to plan input, input to planning and editing the handbook.
5 1 -1 Additional partner contribution
6 2 4 Liaison with WP leader to plan sources, monitor progress and link to relevant pedagogical development.
7 2 6 Planing liason for web based games. Review of materials and suggestions, liaison with external pedaogical adviser.
8 0 2  No input required yet.
9 2 6  Liaison with BETT conference organisers. Input to planing flyear and publicity brochures.
Total 26.5 39.5  
Sub-contract Tech 50%-6000 50%  Separate reporting
Sub-contract Ped 25% - 3000 75% Separate reporting

 Research and training days used

Work package
Days used Balance Comment
1 0 0 No days allocated
2 22 11 Support for e-learning development materials and assessor training, e-mail support and partner trainining sessions. Modifications to meet e-skills changing requirements.
3 2 4 Researching Eurybase for relevant info. Proof read and feedback on questionnaire
4 5 6 Training in the use of Drupal/content management.  Research national frameworks and  link to assessor guidance
5 0 0 No days allocated
6 2 3 Research up to date UK sources eg Open Source Schools Project Feb/March
7 2 8 Drafting model for puzzle documentation, checking puzzles.
8 0 10  No resources yet used
9 6 18

 Attend BETT conference. Assist Spanish partner with preparation of publicity folder
Preparation of text and design for information guide leaflet

Totals 39 60 Any shortfall made up from additional partner contribution

Technical support - Subcontract

Extend certification site to include regional management

Prepare certification and learning sites for language translations

Day to day support for technical issues

Improve front page

Enhance user-interface and help files

January 2010 - March 2010.  - 6000 Euros paid in 2 installments

Administration

Work package
Days used Balance Comment
1 5.5 16.5  Support for management.
2 2 5 Travel arrangements and supporting e-learning development
3 2 0  Support for web questionnaire on web site.
4 5 12  Print and proof handbook, liaison with WP leader.
5 0 0  No allocation
6 2 3  Support for info gathering and documentation
7 2 8  Puzzle development support
8 0 0  No input yet
9 3 10  Support flyers for BETT and general distribution.
Totals 21.5  54.5  

Travel and subsistence

Work package
Travel
Balance Subsistence Balance Comment
1 214.40 1385.60 420 4860 75% of these figures is grant
2 143.98

856.02

 

692 2467  
3 0 0 0 0 No travel budget allocated
4 0 0 0 0  
5 0 0 0 0  
6 0 400 0 1038  Not yet started
7 0 0 0 0  
8 0 0 0 0  
9 0 1600 0 5280 Mainly for conferences and exhibitions in Y2.
Misc costs   Room hire in Prague
Totals  358.38

 4241.62

1112.00

 13645.00

 

 

External Pedagogical Support - Subcontract

Meet with project manager

Review existing NWLG support materials

Review pedagogical model

Write report with recommendations

December 209 - March 2010.  3000 Euros